In the beginning..

This is Wychwood Cottage near Charlbury in the Cotswolds. It was built in 1630 when Charles I was on the throne, and 387 years and 16 monarchs later, on 13th September 2017, became the first home of our own, and our first renovation project.

View from the garden on day 1

Floor plan

It is in a hamlet of 86 residents (not dissimilar to where we live now) and Wychwood Cottage is on a quiet no-through lane with no name leading down to a footpath to fields, woods and a river.

The project

We have three months to get as much of the work done as possible before we move in in mid-December.

The work will include:

  • putting in a joist to support the living room ceiling where an earlier wall (between the two original cottages) was removed in the mid-C20th without adequate support
  • Levelling two sloping bedroom floors
  • Damp proofing
  • New windows, including a missing lintel
  • New kitchen
  • Turning a disused doorway in the living room into a hatch with built-in cupboard underneath
  • Turning bedroom 4 into a family bathroom
  • Turning the current tiny shower room into an ensuite for bedroom 2
  • Replacing the top en suite
  • Lining the chimney and installing a wood burner
  • New boiler, hot water tank and radiators
  • Eventually converting part of the front garden for parking
  • Eventually converting half of the double garage into a home office

Before

Living room

Two fireplaces as it was originally two cottages

..one with bread oven

Kitchen

Bedroom 1 (the floor is 5” lower on the right than on the left)

Bedroom 2 (with a similarly sloping floor)

Bedroom 3This is a 1980s extension, the hole is the old outside window

Bedroom 4 (this will be a family bathroom)

Bedroom 5

En suite to bedroom 5

Current family bathroom (this will be an en suite)

Mural at bottom of stairs

Front

Rear (added in the 1980s)

Side showing original lean-to kitchen

Garden

Week 2: Bedroom floors & en suite

The two sloping front bedroom floors were levelled by laying tapered joists on the floor and bolting them to the wall on the inside (low) end, before laying floorboards on top, creating a void that we could fill with insulation for heat and noise from downstairs.

Prepping bedroom 1: the exposed wall reveals the original lath and plaster construction.

On the first day the builders misunderstood the foreman’s instruction and raised the floor by 12”, making a huge step and a ceiling I could touch with the palm of my hand.

Rectified the next day

Finished floor with step into room

The solution to keeping the same door for a shorter doorway..

Moving the shower room door into the bedroom to make it an en suite, and reclaiming some bedroom from the old shower room. (Note the three unboarded floor panels to the right of the door. I didn’t and managed to put my whole left leg through one of these into the living room in the dark).

New en suite shower space

Week 3: Damp proofing

One of the biggest jobs is damp proofing the walls on the ground floor and part of the first floor. Because the back garden is raised, the end kitchen wall has earth on the outside and needed to be tanked like a cellar.

Revealing the original damp proofing method in the extension

Peeling off the plaster and backing

The rubble generated

Disused fireplace revealed in bedroom two. The plaster in here was wattle & daub (mud & straw).

Exposed stone everywhere

The waterproof tanking is painted on

Weeks 4 & 5

The damp proofing was completed and the walls replastered, though we can never hang anything substantial on them as to pierce the tanking is apparently like making a hole in a dam.

Nick popping in a new lintel ready for the new windows (though the house had managed this far without one)

Lots of pipe work for the new bathroom going in

Opening up the boxing in the top bathroom

Week 6: the RSJ

The survey and subsequent structural engineer’s report showed that when the dividing wall was removed downstairs, the first floor was left inadequately supported. 40 years of the 25’ oak beam that runs the width of the house being supported by a single pillar under the bedroom wall above had led to a sinking of 5” in each of the bedroom floors. So this week saw the insertion of a steel joist under the bedroom wall above.

Prepping the supporting walls

..including raising the 5’6” kitchen doorway

The RSJ has to go through the existing 400-yr-old oak beam

Ta-dah! No acro props or pillar

Design a site like this with WordPress.com
Get started